NEPA Archives - 鶹TVվ /tag/nepa/ Fri, 15 May 2026 19:13:47 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 When the Landscape Leads: Adaptive Management in a Dynamic Wetland System /when-the-landscape-leads-adaptive-management-in-a-dynamic-wetland-system/ Thu, 30 Apr 2026 02:04:38 +0000 /?p=247665 The post When the Landscape Leads: Adaptive Management in a Dynamic Wetland System appeared first on 鶹TVվ.

]]>

By: Ann Boeholt and Camille Felkins, 鶹TVվ Senior Environmental Managers

Adaptive management is often described as a best practice, but its value is most evident when projects face conditions no plan can fully anticipate. This case study — shared at the — illustrates how flexibility, collaboration and observation helped guide a project in a complex wetland system on Tribal lands.

Salmon, Sovereignty and Fish Passage

Pacific salmon have long been central to the cultures, economies and lifeways of Pacific Northwest Tribes. Over time, however, state highway infrastructure contributed to fragmented aquatic systems, limiting access to historic spawning and rearing habitats.

Since the 1990s, the Washington State Department of Transportation (WSDOT) has worked with Tribes and the Washington Department of Fish and Wildlife to identify and address fish passage barriers across the state highway system. This work accelerated significantly following a 2013 permanent injunction that established a 2030 deadline for replacing approximately 400 barriers — those expected to reconnect roughly 90 percent of the targeted habitat. Today, this ongoing, collaborative effort focuses on restoring connectivity within waterways that often intersect sensitive environmental and regulatory settings.

A Culvert, a Wetland and Changing Conditions

One such project along U.S. Highway 101 involved installing a fish‑passable culvert in 2025 to restore natural stream function. Adjacent to the site was a mosaic wetland system within the Quinault Indian Reservation.

Shortly after construction, a high‑flow event caused nearby Harlow Creek to overtop its banks. Water moved across the newly graded wetland, forming overflow channels and flow paths not anticipated in the original restoration design. While the culvert performed as intended, the surrounding wetland — newly planted and not fully stabilized — responded rapidly to these conditions.

These changes introduced challenges. Permit requirements included specific restoration and stabilization goals designed to meet water quality standards, while the wetland’s natural response made a rigid, prescriptive approach difficult to apply. In addition, the stream’s new flow path through the wetland meant that no in-stream work could occur until the following summer construction window. Any potential retrofit work within the wetland or stream would also require careful coordination, as these conditions coincided with the federal government shutdown in fall 2025.

Managing Complexity Through Collaboration

Responding effectively required close coordination among WSDOT, Tribal partners and multiple regulatory agencies. Additional constraints, including narrow in‑stream work windows and limited agency availability, reinforced the need for an approach that was both practical and adaptive.

Rather than attempting to force the system back to its original design assumptions, the project team proposed a flexible, adaptive path forward.

Letting the System Inform Solutions

In the near term, the team implemented minimal erosion‑control best management practices to protect the site while limiting additional disturbance. At the same time, they committed to ongoing monitoring to better understand how the wetland functions under post‑construction conditions.

Monitoring showed that the new overflow channels aligned with the wetland’s mosaic character. While the final design solution is still evolving, the longer‑term approach shifted toward stabilizing those channels within the floodplain — supporting ecological function and permit objectives while working with natural processes.

Together, these decisions reflect how adaptive management can support effective outcomes in dynamic environments by allowing real‑world conditions to inform design, permitting and long‑term performance.

Join Us at NAWM

We will share additional lessons learned from this case study during our presentation, “Implementing effective adaptive management to meet project goals in the face of unforeseen and changing conditions,” at the on Thursday, April 30, at 11 a.m.

If you are attending NAWM, we invite you to join the session and connect with us or continue the conversation on LinkedIn.

Brett Haggerty

Ann Boeholt

Professional Wetland Scientist

Ann Boeholt, Professional Wetland Scientist, is a Senior Environmental Manager at 鶹TVվ Technical Consultants with more than 37 years of experience in wetland ecology, environmental permitting and natural resource management in the Pacific Northwest. She has led local, state and federal permitting efforts for complex infrastructure and restoration projects, with a strong focus on wetlands, aquatic resources and fish passage. Ann has worked extensively with Tribal governments, transportation agencies and regulatory partners, bringing a collaborative and adaptive approach to projects in sensitive environments.

Brett Haggerty

Camille Felkins

Senior Environmental Manager

Camille Felkins is a Senior Environmental Manager at 鶹TVվ with more than a decade of experience supporting infrastructure and restoration projects in environmentally sensitive settings across the Pacific Northwest. Her work focuses on environmental permitting, compliance and construction support for projects involving wetlands, aquatic resources and fish passage. Camille brings a collaborative, practical approach to working with state agencies, Tribal partners and regulatory stakeholders and has expertise in adaptive management strategies that respond to changing site conditions while protecting ecological and community values.

The post When the Landscape Leads: Adaptive Management in a Dynamic Wetland System appeared first on 鶹TVվ.

]]>
From the Field to the Frontlines of Policy: Q&A with Alexandra Davis, Engineering Georgia Magazine’s 2025 “35 Under 35 Women to Know” Honoree /from-the-field-to-the-frontlines-of-policy-qa-with-alexandra-davis-engineering-georgia-magazines-2025-35-under-35-women-to-know-honoree/ Mon, 11 Aug 2025 15:49:42 +0000 /?p=246840 The post From the Field to the Frontlines of Policy: Q&A with Alexandra Davis, Engineering Georgia Magazine’s 2025 “35 Under 35 Women to Know” Honoree appeared first on 鶹TVվ.

]]>

When Alexandra Davis volunteered to write her first National Environmental Policy Act (NEPA) document, she didn’t realize she was stepping into a new future. Before that, she’d been digging deep — literally. Trained as an archaeologist, Alexandra spent years unearthing human history at excavation sites in Malawi, Africa, contributing to discoveries featured in The New York Times.

That one document marked a turning point, shifting her focus from uncovering the past to shaping the future. Now, as NEPA Services Lead at 鶹TVվ, Alexandra helps navigate federal requirements that determine whether critical infrastructure improvements can proceed, analyzing everything from wetland impacts to community displacement to ensure Georgia’s transportation improvements protect both people and natural resources.

Her work sits at the intersection of science, policy and community advocacy, influencing the infrastructure that connects Georgia’s communities. Recently, this impactful work earned Alexandra recognition as one of Engineering Georgia Magazine’s 2025 “35 Under 35 Women to Know,” an honor celebrating young leaders who are redefining the future of engineering.

Q: Let’s go back to the moment you first said yes to writing a National Environmental Policy Act (NEPA) document. What were you thinking, and did you know then it would change everything?

I was only 24 when I was offered the opportunity to work on NEPA documents, and honestly, at the time, I was just focused on staying employed and continuing to learn. It was right at the start of the COVID-19 pandemic, so job security was at the front of my mind. I figured if I could cross-train and make myself valuable to the team, I’d have a better shot at holding onto my position. It wasn’t an immediate career-defining moment. It took about two years of working in NEPA and three years at 鶹TVվ for me to realize that this path was going to reshape my career in ways I hadn’t expected. And I’m so grateful I said yes to that opportunity.

Q: You started your career excavating ancient remains in Africa. How did that path lead you to shaping policy through NEPA at 鶹TVվ?

As an archaeologist, my work required not only excavating ancient remains but also being a strong technical writer and researcher, digging up information about the past, analyzing complex data and translating those findings into detailed reports. Those skills transferred directly to environmental consulting work. About a year after I started at 鶹TVվ, my manager offered me the opportunity to begin authoring NEPA documents. I’ve always been eager to learn and grow, so I jumped at the chance. In addition to writing, I began coordinating with the Georgia Department of Transportation as a NEPA Analyst. It didn’t take long for me to realize that I had a real love for Environmental Project Management and, surprisingly, for the fast-paced, ever-changing nature of juggling multiple projects at different stages. While it might seem like a big shift from excavating ancient remains, both roles require attention to detail, problem-solving and a deep respect for our environment and history.

Q: As NEPA Services Lead, what major projects or initiatives have you led since your promotion?

Since my promotion, I’ve taken on leadership of all NEPA projects in Georgia, overseeing environmental compliance for more than 75 transportation projects. One of the most notable efforts has been managing and coordinating nine GDOT bridge replacement projects, which have required near-daily coordination and problem-solving. A major challenge on that effort was receiving Notice to Proceed later than expected and having to recover the schedule. This meant accelerating the environmental process for archaeology, history and ecology without compromising our quality standards. This experience showed me how important it is to build flexibility into our environmental review processes and maintain careful oversight. Beyond project work, I’ve also been leading initiatives within 鶹TVվ’ Southeast region to strengthen connections between young professionals and current college students.

Q: How do you balance protecting the environment with supporting the needs of the communities connected to it?

On our larger GDOT projects, especially those involving new location roadways and potential displacements, it takes a lot of public involvement and coordination to address community concerns. In some cases, this has even led to redesigning project alignments to better serve the environment and the people impacted. Balancing these priorities requires constant, open communication between the design team, including the project manager, lead designer, traffic engineers and the environmental team. On the other hand, many of our bridge replacement projects tend to have minimal environmental impact and generally receive strong community support, which makes those collaborations much smoother.

Q: You’ve been named one of Georgia’s 35 Women to Know. What do you hope stands out about how you lead and connect with others?

My goal is to lead with kindness, empathy and flexibility. It’s important to me that the people I work with feel supported, heard and valued. I always want to be the kind of leader who makes time for questions, concerns, or just a quick conversation. I also believe work should be enjoyable. I truly love what I do at 鶹TVվ and the people I work with, and I want my team to feel that same sense of purpose and enjoyment in their roles.

Alexandra’s career may have started with a shovel in the ground, but her greatest impact may lie in what she is building — collaborative teams, thoughtful policies and space for more voices to shape the future. Her story reminds us that engineering is about more than equations or approvals. It’s about people, purpose and vision.

Discover how our environmental services can support your next project, or follow Alexandra’s lead and join our growing team.

Brett Haggerty

Alexandra Davis

NEPA Services Lead

Alexandra Davis manages environmental compliance and NEPA documentation for transportation projects across Georgia. She started at 鶹TVվ as an archaeologist in 2019 after completing fieldwork in Malawi, Africa. Alexandra transitioned to environmental policy work, coordinating with state agencies and developing process improvements that enhance project delivery. Alexandra has enabled the seamless delivery of 75+ transportation projects across Georgia. She holds a BA in Anthropology from Emory University and has completed training through the National Highway Institute. When she’s not working, you can find Alexandra participating in Gwinnett County wetland cleanups or bowling strikes with the ASHE league.

The post From the Field to the Frontlines of Policy: Q&A with Alexandra Davis, Engineering Georgia Magazine’s 2025 “35 Under 35 Women to Know” Honoree appeared first on 鶹TVվ.

]]>
Building a Much-Needed Bridge in Baton Rouge /building-a-much-needed-bridge-in-baton-rouge/ Thu, 28 Sep 2023 16:05:29 +0000 /?p=244203 Testing, Inspection and Certification

The post Building a Much-Needed Bridge in Baton Rouge appeared first on 鶹TVվ.

]]>

Building a new bridge across the Mississippi River in the Baton Rouge area is not a new idea. The need had been there for decades, but getting beyond general conception has proved difficult, for any number of reasons. But today, thanks to a more pragmatic approach to achieving this monumental undertaking, a new Mississippi River Bridge (MRB)-building effort is taking those first critical steps toward becoming reality.

“Some of the attempts over the past 20 years have had bigger ambitions and scope and they were never able to get off the ground, either financially or politically,” says Kara Moree, CFM. “What we’re doing is concentrating on the early phases—selecting a location and getting the environmental documentation—to provide a foundation and build momentum for the project. This approach has been very successful in moving it forward.” Moree is the national director for NEPA & environmental compliance with 鶹TVվ Technical Consultants and serves as the overall project manager. 鶹TVվ was selected by the Louisiana Department of Transportation & Development (LADOTD) as the prime consultant to conduct an Enhanced Planning Investigation and Environmental Evaluation for a new river bridge, one of the most high-profile civil infrastructure projects in the state of Louisiana.

Project staff members answer questions from the public about the new
Mississippi River Bridge at a community center meeting in April 2022.

As its first order of business, the 鶹TVվ-led team was asked to identify approximately 30 possible locations for the new bridge. The project limits were set along 60+ miles of river so, at first glance, it did not appear to be a tall order, but they didn’t get too far into the navigation study before discovering just how many constraints the project would be subjected to. “There were a lot of places we couldn’t put piers in the river. There are anchorages and things of that nature that we needed to stay away from. We were also limited to a 2,000 ft maximum main span length. We consulted with the U.S. Coast Guard and spoke with river pilots and identified other restrictions and impediments. It was difficult coming up with 30 locations, but eventually, we did identify 32,” Moree says.

From there, the team took a tiered approach to narrowing that list down to a more manageable number. Two rounds of screening were conducted in consideration of the project’s purpose and need, which was informed and supported by traffic data and other analyses. “We also had to consider the environmental impacts. We had to determine if we would be able to get permits, whether it was for wetlands or levees or the Coast Guard. There’s also a lot of really big industry up and down the river, and of course, Baton Rouge has one of the busiest ports in the world,” she says. By taking a data-driven approach, the team, which included 13 sub-consultants, was able to back up their decisions with cold facts. This proved particularly beneficial when 10 preliminary alternatives were selected and presented to the public.

As in many areas of Louisiana, Baton Rouge is still dealing with the aftermath of Hurricane Katrina in 2005. Almost overnight, the area took in an additional 200,000 displaced individuals. One of the impacts of that growth was that the metropolitan area hit its projected 2030 traffic volumes 25 years ahead of schedule. A project of this size and potential impact is bound to raise the interests, and passions, of residents and community leaders. Extensive public information and stakeholder engagement efforts were particularly critical in keeping the project moving forward. The team also made quarterly presentations to a state legislative committee so that government and political influencers would be kept abreast of progress.

Although 鶹TVվ is a national firm with 100 locations across the country, the MRB project has benefited from a decided home-field advantage. Both Moree and Maria Bernard Reid, NEPA specialist and deputy project manager were born and raised in south Louisiana. Although 鶹TVվ is a multi-disciplined firm with the resources to complete a project of this magnitude from start to finish, it benefited from the specialized expertise of its two project leads. “We are not engineers—we’re environmental people. Everything we see, we see through the eyes of biologists and NEPA practitioners. The Federal Highway Administration, who will be reviewing our environmental document, really appreciates having that perspective informing our findings,” says Reid.

That advantage has resulted in what will be the first approved Planning and Environmental Linkages (PEL) document on a LADOTD project. The integrated and collaborative PEL approach asks project teams to consider environmental factors during the planning process, using data and analysis gathered during planning to enhance the environmental investigations and analysis. FHWA encourages its use as a means to save time and cost by minimizing duplicate efforts. “Going straight from planning into NEPA, we fully expect that all of our work will be brought forward. Having two environmental professionals leading that has been a very big plus in producing high-quality and approvable documents,” Reid says.

鶹TVվ is scheduled to complete its work on the MRB project in late 2024. A new governor and administration will be installed in January, and the team is focused on keeping the project moving forward and maintaining the state’s commitment. If all goes according to plan, it will soon be moving toward design and construction.

Published by Engineering News-Record (ENR)
On July 31, 2023

 

The post Building a Much-Needed Bridge in Baton Rouge appeared first on 鶹TVվ.

]]>
Sackett v. EPA Supreme Court Decision Early Analysis of the Effects on Wetland Jurisdiction /sackett-v-epa-supreme-court-decision-early-analysis-of-the-effects-on-wetland-jurisdiction/ Tue, 06 Jun 2023 18:19:02 +0000 /?p=243916 The post Sackett v. EPA Supreme Court Decision Early Analysis of the Effects on Wetland Jurisdiction appeared first on 鶹TVվ.

]]>

On May 25, the US Supreme Court issued a decision in the Sackett v. EPA case, a 14-year-long lawsuit over property rights and the legality of building on federally protected wetlands. All nine Justices agreed that the wetlands on the Sackett’s property should not fall under the jurisdiction of (CWA), permitting the Idaho couple to continue with construction of their new residence.

But there were substantial differences in the approach to the scope of the decision.

Justice Alito wrote the opinion for the five justice majority, which included Justices Barrett, Gorsuch, Roberts, and Thomas (note that Justices Thomas and Gorsuch prepared a separate concurring opinion).

Justice Kagan filed an opinion concurring with the judgement in favor of the Sacketts, but offered a more inclusive approach to the question of what wetlands should fall under federal jurisdiction. Justice Kagan was joined by Justices Jackson, Sotomayor, and Kavanaugh.

Background

The Sackett’s legal battle began in 2007, when they started earthmoving activities to prepare a 0.63-acre lot they owned near Priest Lake, Oregon.

The family received a notice from the Environmental Protection Agency (EPA) to stop work to avoid impacts to wetlands on the property. The EPA based their jurisdictional decision on their conclusion that the wetlands on the Sackett’s lot drained into a non-navigable creek that then led to Priest Lake.

The Sacketts challenged EPA’s decision, and the various cases worked their way through the federal courts, ending with the 9th Circuit issuing an opinion that there existed a “significant nexus” between the wetland on the Sackett’s property and Priest Lake. On May 25, the Supreme Court overturned that decision and essentially voided the “significant nexus test.”

Summary of the Decision

Justice Alito ruled that courts should apply a more stringent test, outlined by four justices (Alito, Chief Roberts, Scalia, and Thomas) in a previous case (Rapanos v. United States). Alito relied heavily on Justice Scalia’s opinion, in which he wrote that the Clean Water Act (CWA) applies to a particular wetland only if it blends or flows into a neighboring water that is a channel used in interstate commerce — generally referred to as a Traditionally Navigable Water (TNW).

The majority wrote that the text of the CWA defined “Waters of the United States” (WOTUS) as “geographical features” ordinarily described as “streams, oceans, rivers, and lakes.” The statute also clearly states that WOTUS includes wetlands that are “adjacent” to another WOTUS.

For decades, this meant that wetlands could fall under Section 404 even though they were separated from a TNW, provided there was some direct connection to that TNW. Thus, a wetland that was connected by even an ephemeral stream, through the greater stream network, eventually emptying into a TNW, fell under federal regulation.

Justice Alito, in adopting Scalia’s strict definition of adjacency from the Rapanos decision, wrote that wetlands can only fall under federal regulation if they possess a direct, relatively permanent connection to another WOTUS. Still, Alito seemed to indicate that to be adjacent, a wetland must be “indistinguishably” part of a stream, ocean, river, or lake.

Potential Effects

The US Army Corps of Engineers (Corps) and the EPA are expected to revise the WOTUS Rule once again. The rule recently enacted by the Biden Administration does not incorporate Justice Alito’s new, much narrower definition. The previous definition of WOTUS, one that has been in practice since 1986, also will not meet the new test in Alito’s decision.

It is clear so far that a wetland that is congruent with a stream or other regulated body of water will still fall under federal jurisdiction. It seems clear that a wetland that is adjacent to relatively permanent streams (intermittent or perennial streams) will also still be regulated, but that ephemeral streams would likely not be (ephemeral streams are not jurisdictional under the 1986 guidance). Furthermore, a wetland that is connected by a relatively permanent stream to a TNW should still be regulated.

The decision will most likely expand the definition of “isolated wetlands,” by removing from jurisdiction those wetlands that previously exhibited a “significant nexus” to another WOTUS. The attached diagram shows 鶹TVվ’ interpretation of the decision based on information we have to date.

Note that state wetland regulations still apply until changed by the individual state administrations or legislatures.

The index below lists the WOTUS definition that is currently applicable in each state. This will likely change as the Corps and EPA establish new rules and guidance following the Sackett Decision.

Author:
Jim Kooser
鶹TVվ Senior Ecologist,
Wetlands and Natural Resources Management

The post Sackett v. EPA Supreme Court Decision Early Analysis of the Effects on Wetland Jurisdiction appeared first on 鶹TVվ.

]]>
鶹TVվ Awarded $15 Million Maximum Value Contract to Support Georgia Department of Transportation’s Railroad Safety Program /atlas-awarded-15-million-maximum-value-contract-to-support-georgia-department-of-transportations-railroad-safety-program/ Fri, 06 Jan 2023 17:16:48 +0000 /?p=244045 The post 鶹TVվ Awarded $15 Million Maximum Value Contract to Support Georgia Department of Transportation’s Railroad Safety Program appeared first on 鶹TVվ.

]]>
AUSTIN, Texas, Jan. 06, 2023 (GLOBE NEWSWIRE) — 鶹TVվ Technical Consultants, Inc. (Nasdaq: ATCX) (“鶹TVվ” or the “Company”), a leading Infrastructure and Environmental solutions provider, announced today that it was selected by the Georgia Department of Transportation’s (GDOT) Railroad Safety Program to provide Engineering & Design and Environmental services related to rail crossings owned by one of the largest Class 1 rail operators in the state. The contract has a maximum value of $15 million with an initial term of three years, and an option for a two-year extension.

GDOT’s Railroad Safety Program mission is to identify, reduce and eliminate hazards at at-grade railroad crossings throughout the State through the installation of warning device equipment, crossing consolidation, and roadway and striping improvements to crossing approaches and grade separations. Under the contract, 鶹TVվ’ technical staff will conduct field inventory of railroad crossings, provide concept, preliminary, and final design plans for prioritized projects, as well as prepare National Environmental Policy Act (NEPA) studies.

“鶹TVվ has partnered with GDOT for over 16 years, providing our full portfolio of services to various transit-related markets throughout the state,” said 鶹TVվ CEO, L. Joe Boyer. “We are excited to continue our work under GDOT’s railroad safety program and with major rail operators in our shared efforts to improve the safety and efficiency of Georgia’s transportation infrastructure.”

About 鶹TVվ Technical Consultants
Headquartered in Austin, Texas, 鶹TVվ is a leading provider of Infrastructure and Environmental Solutions. We partner with our clients to improve performance and extend the lifecycle of built and natural infrastructure assets stressed by climate, health, and economic impacts. With 3,500+ employees nationwide, 鶹TVվ brings deep technical expertise to public- and private-sector clients, integrating services across four primary disciplines: Environmental (ENV); Testing, Inspection and Certification (TIC); Engineering & Design (E&D); and Program Management/Construction Management, and Quality Management (PCQM). To learn more about 鶹TVվ innovations for transportation, commercial, water, government, education, and industrial markets, visit.

Forward-Looking Statements
The statements contained in this press release that are not purely historical are forward-looking statements. Our forward-looking statements include, but are not limited to, statements regarding our management team’s expectations, hopes, beliefs, intentions or strategies regarding the future. The information included in this press release in relation to 鶹TVվ has been provided by 鶹TVվ and its management team, and forward-looking statements include statements relating to 鶹TVվ’ management team’s expectations, hopes, beliefs, intentions or strategies regarding the future. In addition, any statements that refer to projections, forecasts or other characterizations of future events or circumstances, including any underlying assumptions, are forward-looking statements. The words “anticipate,” “believe,” “continue,” “could,” “estimate,” “expect,” “intends,” “may,” “might,” “plan,” “possible,” “potential,” “predict,” “project,” “should,” “would” and similar expressions may identify forward-looking statements, but the absence of these words does not mean that a statement is not forward-looking. The forward-looking statements contained in this press release are based on our current expectations and beliefs concerning future developments and their potential effects on us and are based on management’s experience and perception of historical trends, current conditions, anticipated future developments and other factors believed to be appropriate. There can be no assurance that future developments affecting us will be those that we have anticipated. These forward-looking statements involve a number of risks, uncertainties (some of which are beyond our control) or other assumptions that may cause actual results or performance to be materially different from those expressed or implied by these forward-looking statements. These risks and uncertainties include, but are not limited to: (1) the effect, impact, potential duration or other implications of the COVID-19 pandemic and any expectations we may have with respect thereto; (2) the risk that our actual results may differ from the guidance we have provided; (3) the ability to recognize the anticipated benefits of our past acquisitions, which may be affected by, among other things, competition, the ability of the Company to grow and manage growth profitably, maintain relationships with customers and suppliers and retain management and key employees; (4) changes adversely affecting the business in which we are engaged; (5) changes in applicable laws or regulations; (6) the possibility that the Company may be adversely affected by other economic, business, and/or competitive factors; and (7) other risks and uncertainties indicated from time to time in the Company’s filings with the U.S. Securities and Exchange Commission, including those under “Risk Factors” therein.

Contacts:

Media
Karlene Barron
770-314-5270

Investor Relations
Chase Jacobson, Vallum Advisors
512-851-1507

The post 鶹TVվ Awarded $15 Million Maximum Value Contract to Support Georgia Department of Transportation’s Railroad Safety Program appeared first on 鶹TVվ.

]]>
Working, Restoring Pacific Northwest Salmon Habitat /working-restoring-pacific-northwest-salmon-habitat/ Mon, 01 Aug 2022 18:22:15 +0000 /?p=243353 Testing, Inspection and Certification

The post Working, Restoring Pacific Northwest Salmon Habitat appeared first on 鶹TVվ.

]]>

鶹TVվ, O’Neill Service Group and partners are driving Salmon recovery in the Pacific Northwest.

State and local habitat enhancement dollars are funding the rebuilding of critical infrastructure to better serve fish and human populations. Salmon are a critical part of the region’s ecology and culture; 鶹TVվ is positioned to be a part of its recovery.

Washington State Department of Transportation’s program to replace more than 400 non-conforming culverts beneath state highways is one of these programs. 鶹TVվ is developing National Environmental Policy Act documents, Section 404 and 401 permit applications, performing quality assurance and environmental/material testing for these projects to restore hundreds of miles of historic breeding and rearing habitat statewide. Fish have already returned to stream habitat above the repaired culvert replacements. 鶹TVվ is under contract for 35 culvert replacement projects in Washington.

As construction manager for King County, 鶹TVվ is also removing old levees and reestablishing critical floodplain habitat along the region’s major rivers. The levee setback program is a major win for both salmon and the local communities, improving flood protection function and reconnecting habitat. Historic runs of chum salmon are returning to newly created channels like the one at Lones Levee Setback and Floodplain Restoration Project.

鶹TVվ looks forward to many years of important restoration in the Pacific Northwest.

Published by Engineering News-Record (ENR) – Environmental Management
On August 1, 2022

 

The post Working, Restoring Pacific Northwest Salmon Habitat appeared first on 鶹TVվ.

]]>